Wayfinder / Case study / Modernisation plan

These duration scenarios are planning assumptions, not approved dates.

Indicative modernisation delivery schedule

These are proposed low, central and high working-day scenarios, not dates, a funded plan or committed staffing. Approval and waiting time can change the actual elapsed duration.

Central scenario: 280 working days along the longest planned dependency chain.

Delivery slice
Relative working days
DSL-001 · Recover and Characterize the Executable Baseline30 days · Start
DSL-002 · Establish Measures and Approval Evidence18 days · DSL-001
DSL-003 · Resolve Identity, Relationships and Authorization40 days · DSL-001
DSL-004 · Formalize Lifecycles and Identifiers45 days · DSL-001, DSL-003
DSL-005 · Resolve Calculations and Reference Meanings65 days · DSL-001, DSL-004
DSL-006 · Introduce Modular and Durable Mutation Boundaries55 days · DSL-001, DSL-003, DSL-004
DSL-007 · Secure Files and Preserve Generated Documents40 days · DSL-001, DSL-003, DSL-006
DSL-008 · Establish Reporting and Operational Readiness40 days · DSL-001, DSL-006
DSL-009 · Rehearse Deterministic Migration, Cutover and Recovery70 days · DSL-005, DSL-007, DSL-008

Dependencies and review requirements

The sequence includes access to environments, review by customer subject-matter experts, decisions about business behaviour and representative validation. These scenarios should be recalibrated after the first accepted delivery slice.