Wayfinder / Case study / Modernisation plan

These duration scenarios are planning assumptions, not approved dates.

Indicative modernisation delivery schedule

These are proposed low, central and high working-day scenarios, not dates, a funded plan or committed staffing. Approval and waiting time can change the actual elapsed duration.

Central scenario: 450 working days along the longest planned dependency chain.

Delivery slice
Relative working days
DSL-001 · Establish the Deployed and Measurable Baseline45 days · Start
DSL-002 · Resolve Data Authority and Rehearse Migration50 days · DSL-001
DSL-003 · Deliver the Read-Only Servicing Path55 days · DSL-001, DSL-002
DSL-004 · Modernize Workforce Identity and User Administration45 days · DSL-001, DSL-003
DSL-005 · Establish Reference Data and Servicing Updates65 days · DSL-002, DSL-003, DSL-004
DSL-006 · Cut Over Payments and Transaction Outcomes80 days · DSL-002, DSL-005
DSL-007 · Migrate Authorization, Fraud, Batch, Reporting, and Recovery110 days · DSL-001, DSL-002, DSL-006

Dependencies and review requirements

The sequence includes access to environments, review by customer subject-matter experts, decisions about business behaviour and representative validation. These scenarios should be recalibrated after the first accepted delivery slice.